SWPPP Requirements in Michigan

Michigan has the most complex dual-permit construction stormwater system in the Great Lakes region. Operators must obtain a Part 91 Soil Erosion and Sedimentation Control permit from the county AND NPDES construction stormwater coverage under Part 31 Rule 2190 (permit-by-rule) from EGLE — not a traditional single general permit number. Coverage for sites disturbing five or more acres is typically obtained through a Notice of Coverage (NOC) to EGLE after Part 91; smaller sites often tie to Part 91 and Rule 2190 as described in EGLE guidance. These are separate applications, fees, inspections, and enforcement authorities. Michigan's Great Lakes watershed position makes stormwater quality a top environmental priority.

Data Note: This page contains general guidance for Michigan. We are actively verifying state-specific details. Last reviewed: 2026-04-10. Contact a local consultant for current requirements.

Michigan SWPPP Key Facts

  • Dual requirement: Part 91 county SESC + NPDES coverage under Part 31 Rule 2190 (permit-by-rule — verify current NOC steps in EGLE/MiEnviro guidance)
  • County Part 91 permit is typically required before or in parallel with NPDES coverage steps
  • Two separate inspection regimes: county inspectors (Part 91) and EGLE (stormwater program)
  • State NPDES fees depend on program tier; county Part 91 fees vary significantly
  • Great Lakes watershed jurisdiction adds federal Great Lakes Compact considerations

Administering Agency

Agency
Michigan Department of Environment, Great Lakes, and Energy (EGLE)
Phone
800-662-9278

Permit Details

Permit Name
NPDES construction stormwater coverage (Part 31, Rule 2190 — permit-by-rule; not a single statewide permit number)
Permit Document
View Current Permit

SWPPP Thresholds & Triggers

Acreage Threshold
1 acre of land disturbance

Michigan requires BOTH a county-issued Part 91 Soil Erosion and Sedimentation Control (SESC) permit AND NPDES construction stormwater coverage under Part 31 Rule 2190 (permit-by-rule). The Part 91 SESC permit from the county is typically required first. Great Lakes watershed protections apply statewide.

Inspection Requirements

Inspection Frequency
At least once every 7 days and within 24 hours after a storm event producing 0.5 inches or more of rain
Rain Event Threshold
0.5 inches in 24 hours
Certified Inspector
Required by state
Accepted Certifications
CPESC, CESSWI, Michigan SESC-certified inspector

Part 91 inspections are conducted by county agencies; NPDES inspections by EGLE. Two separate inspection regimes operate in parallel.

Penalties & Enforcement

Max Civil Penalty (Per Day)
$25,000 per day per violation (Part 31 Water Resources Protection Act)
Criminal Penalties
Felony charges for knowing violations; imprisonment up to 2 years

Both county (Part 91) and EGLE (NPDES) can issue enforcement actions independently.

Permit Fees

NOI Filing Fee
$0 (state NPDES); Part 91 county fees vary ($100–$2,000+ depending on project size and county)
Other Fees
Part 91 bond or financial assurance may be required by county

How Michigan Differs from Federal Requirements

  • Michigan's dual-permit system (Part 91 + NPDES) has no federal CGP equivalent — federal permit only covers the NPDES component.
  • Part 91 county permits add a sub-state regulatory layer unique to Michigan.
  • EGLE's Great Lakes mandate creates stricter water quality standards than federal CGP baseline.

SWPPP Tips for Michigan

  • Apply for the county Part 91 SESC permit first — EGLE may require proof of Part 91 application before processing the NPDES NOI.
  • County SESC requirements vary significantly; contact the county drain commissioner or conservation district early.
  • Budget for Part 91 bond requirements — some Michigan counties require performance bonds for larger projects.

Michigan SWPPP FAQs

Do I need both a county and a state permit in Michigan?+

Yes. Michigan law requires a Part 91 Soil Erosion and Sedimentation Control permit from the county AND NPDES construction stormwater coverage under Part 31 Rule 2190 from EGLE for projects disturbing 1+ acre, following EGLE's permit-by-rule process (including Notice of Coverage for larger sites).

Which permit do I get first — the county Part 91 or the state NPDES?+

Generally the county Part 91 permit comes first. EGLE may require the Part 91 application to be submitted or approved before NOC/NPDES steps. Check with your specific county and EGLE district office.

Find a SWPPP Consultant in Michigan

Tell us about your project and we'll connect you with a qualified environmental consultant — free, no obligation.

We'll only call if you ask us to.

Free, no-obligation match. Your info is kept confidential.